Friday, 10 February 2017

Weekend Update

A really busy week on the course with drying conditions allowing us to press ahead with the construction and turfing on the 1st tee.

The 1st has been a really big project, which we started in November and has had many stages. Clearance, drainage, irrigation, shaping and the routing of the new paths as well as the provision of a buggy/trolley park. The weather has always dictated the pace of the work and recently we have managed to finish shaping and moving the rootzone material onto the new Ladies/Winter tee. This week we laid over 500 sq/m of turf and I estimate another 300 m will finish the job next week. The Rubber/aggregate path material is due to be laid by the contractors on or around the  22/23 February, as always this will be weather dependent. Soon after this, the tarmac will be laid near the Pro's shop.
The Tee will be in play for the Lady Captains drive-in and should provide a much improved surface.

Next week, we plan to carry out some early renovation work on the greens. Hollow-tining, over-seeding, top-dressing and the application of a granular fertiliser will all hopefully be completed. We hope this will provide the  greens with everything they need for an early improvement in the surfaces.

Fingers crossed the forecast snow flurries don't materialise for the weekend.

Mark & the Greens team.

Friday, 20 January 2017

Weekend Update.

The weather has really improved today, with almost spring like conditions. Much better than the drizzle, fog and cloud earlier in the week.

The Greens were slit on Monday & Tuesday to help keep the surfaces open and aid drainage. This was followed by a cut with the hand mowers (which we always try to use during the winter months) to restore the surfaces. The penetrant is still helping reduce the dew in the mornings and this will also help the greens fend of any disease outbreaks.

The construction work on the 1st tee continues when conditions allow, the surfacing of the paths will take place in late February/early March as temperatures need to be higher for the materials to look their best. The bank at the front of the Men's tee will be turfed next week and more work will be carried out on the Ladies/Winter tee, including the installation of sprinklers.

The bunker renovation work continues with the 10th greenside bunkers being dug out and prepared for turf. The turf will be delivered next week, so that will keep us busy.

The fairways will be slit throughout next week and we will then move onto the approaches and semi-rough. It would probably be better to use your fairway mat on most holes as this can be quite disruptive.

Have a great weekend.

Mark & the Greens team.

Friday, 23 December 2016

Christmas Update.

A busy few weeks, with favorable weather helping us move around the course.
The work has continued on the 1st tee and putting green area. with the new path fully stoned and compacted all the way to the 1st carry. The ground conditions have been testing due to the nature of the infill material used when the Ladies tee was constructed. The base of the new Ladies/Winter tee has been formed and covered with drainage stone. The next step in early January will be to install irrigation and spread the rootzone ready for turfing in late January. The other paths will then be prepared for the contractors to surface in February/March. As always, this schedule will be heavily dependent on the weather.

The greens have received a micro-tining to keep the surfaces open and aid recovery from the Fusarium in November. They have also been sprayed with a penetrant and a micro nutrient liquid to ward off further disease attacks.
We are continuing to cut them with hand mowers which should keep the surfaces tidy.

The bunker renovation work is continuing, with 2 completed and 2 more in various stages of completion. We are waiting for a turf delivery at the start of January and by then, a couple more should be ready. Some remedial work has also been carried out to the L/H bunker on the 17th green. These areas are GUR until Spring.

Merry Christmas to everybody from the Greenstaff.

Friday, 25 November 2016

Weekend Update

Well the course is drying out nicely following Mondays deluge. FYI we actually had more rainfall in 24 hours ( 46mm ) than we did last Boxing day. The course stood up to it so well, and was open for play the next day on main greens with just buggies restricted.

The greens are continuing their recovery from the Fusarium outbreak and the surfaces are dry and firm. Lets hope the scars fill in some more before the end of the year.
Work has carried on around the 1st tee, with 3 large Sycamore's being removed. I know there is always controversy when we remove trees, but Sycamore's are not a good tree to have close to playing areas on a golf course. The large leaves kill grass in the Autumn, change the nature of soil and grass species and they encourage the development of moss. The roots also cause heave and restrict drainage. 
With the path alterations we intend to complete around the 1st tee, they really did need to be felled.

The Path on the 16th hole has been turfed, but we are awaiting delivery of some more on Monday to complete the work on the 12th. When this has settled we will place the ground stabilisation matting and apply some fertiliser to encourage growth and rooting. Please keep off these areas till recovery is complete.

The course has received some mowing to tidy areas up for the weekend and the bunkers have been raked and sand pushed back up the faces. 

Next week we intend to slit the greens, approaches and start the fairways. Work will also continue on the 1st tee and some bunker renovation.

Enjoy the weekend.

Mark & the Greens team.

Friday, 18 November 2016

Weekend Update

Well, just like last year, the Winter has arrived in the middle of November. As i sit writing this, the course is closed following heavy rain & sleet. The temperature is 4 degrees and more rain/sleet is forecast.


Despite this, we have been busy on the course this week. 
The greens were slit on Monday with little surface disruption. They were also cut & ironed on Wednesday to further restore the surfaces. The Fusarium scars are recovering and the greens certainly look much improved from 2 weeks ago. Lets hope the seedlings continue to develop and fill in the gaps.
We have continued our work on the 12th & 16th paths, with drainage gullies installed, surface preparation work done and turf laid. The plan is to introduce some ground stabilisation material onto these areas the same as we have used on the 4th hole. This should spread the wear and combined with the hard wearing turf should provide sustainable grass walkways. The teeing area on the 12th has been moved to the start of the fairway to ease traffic issues.
The bunkers renovation work has started on the 3rd hole. These bunkers suffer badly from stone contaminated sand and overhanging faces. They will be lined to prevent this and filled with fresh sand. We plan to rebuild 9 more across the course.
More work has been carried out on the 1st tee, but conditions are difficult due to the weather. When conditions improve, the drainage carpet for the new tee will be installed and more work on the paths will be carried out.


Have a great weekend.


Mark & the Greens team.

Tuesday, 15 November 2016

Weekend Update

A difficult week weather wise, with heavy frost and persistent rain. The course was closed for 3 hours on Wednesday and all day Thursday. The water is just not moving through the soil profile following a drier than average September & October. When we slit the fairways last week, the blades were not going all the way in due to the compaction in the soil. Hopefully, conditions will improve following more aeration.
The 1st tee is now roughly shaped and the new Tee to fairway path has been shaped. Work will continue when the weather allows. 
We have started digging out some of our stone paths, with the 12th & 16th being the first. We plan to remove all the stone in these areas, creating a wider turf path which will feature ground stabilisation material and hardy Rye grass. We hope that these paths will provide a long lasting, relatively maintenance free alternative to stone paths. If successful, we will convert more paths to turf.

Fingers crossed for the weekends weather.

Mark & the Greens team.

Friday, 4 November 2016

Course Update.

As you will no doubt be aware, the greens have suffered an attack of Fusarium Patch disease.
Fusarium is a constant threat throughout the Autumn and only needs the right conditions to take hold.
Unfortunately, the late timing of the renovation work has provided the perfect conditions for an outbreak.

The sand applied to the greens to fill the tine holes has smothered the grass plant and because of the damp, dewie conditions the base of the turf has been infected and the disease has spread throughout the plant. The damp conditions at this time of year make it difficult to work the sand into the putting surfaces, reducing the chance of an attack. This has been exaggerated by weather fronts coming from the east, which have reduced soil temperatures leading to slow growth and little recovery from the renovation work. 
We regularly spray Fungicide to prevent these attacks, but turf covered in sand offers little leaf for the chemicals to attach to and prevent the disease.
There are 2 types of Fungicide:-  Contact, which lands on the active disease and kill it instantly, but offers no further prevention and Systemic, which is absorbed into the plant and inoculates it against further attack.
We have sprayed Systemic Fungicide 3 times this Autumn (last on 28/10/16)  and a Contact this Tuesday.  Each application costs between £750 & £600.
Members regularly ask me why we renovate greens in the playing season and sadly the reason is now plain to see.
On a positive note, the grass which has been killed is the weaker Annual Meadow grass (Poa Annua) and the seedlings from the renovation work are now coming through to take their place. A granular fertiliser has been applied as well as Iron and a penetrant wetting agent. These should help speed up recovery as long as Mother Nature does her bit.

The 1st tee renovation project is now under way. The plans will be posted onto the notice boards as soon as we receive an updated version from the Club's architect. 

Mark & the Greens team.